FusionModule1000A40 Prefabricated All-in-One Data
Center
Installation Guide
5 Installing External Accessories for Pre-fab. Modules
Issue 03 (2020-06-09)
Copyright © Huawei Technologies Co., Ltd.
34
Figure 5-2
Installing the external cable tray
----End
5.2 (Optional) Installing Awnings
Prerequisites
The pre-fab. modules have been installed.
The position for installing the awning has been specified.
Context
An awning must be installed on the top of the main entrance door to prevent rainwater from
entering the pre-fab. module when the door is open.
Preparations
Tools: socket wrench, Phillips screwdriver, glue gun, step ladder
Materials: awning, awning mounting plate, rubber pad, white sealant, awning bolt
Skill requirement: common technician