FusionModule1000A40 Prefabricated All-in-One Data
Center
Installation Guide
2 Site Requirements
Issue 03 (2020-06-09)
Copyright © Huawei Technologies Co., Ltd.
2
2
Site Requirements
2.1 Site Selection Requirements
The power supply is stable and reliable.
The communication and traffic are convenient.
The site is far away from dust, smoke, harmful gas, and corrosive, flammable, or
explosive objects.
The site is not on a low-lying land, and above the highest water level of that area.
The site is far away from sources of strong variation, loud noises, and strong
electromagnetic interference.
The ground is solid without spongy or soft soil, and is not prone to water aggregation or
subsidence.
The site is in an open area, meets the pre-fab. module installation and maintenance
requirements, and meets the heat dissipation requirement of the smart cooling product
outdoor unit. For details about the space requirements, see the installation position
diagrams in the quick installation guide for the solution in use.
The site is at least 50 m away from residential areas.
The site is far away from a class D environment or 500 m away from the seashore.
For a specific project, select the product specifications based on the application environment. For
example, in a class B environment 3700 m away from the seashore, the smart cooling product outdoor
unit can be a common outdoor unit. In a class C environment 500–3700 m away from the seashore, the
smart cooling product outdoor unit must be a class C outdoor unit.
2.2 Field Requirements
The FusionModule1000 can be installed on bases or concrete platforms depending on the
actual scenario. The site requirements vary with the selected installation mode.
2.2.1 (Optional) Concrete Platform Scenario
Build concrete platforms on the selected installation site.