All partitions on the disks must be formatted as NTFS.
Cluster installation
During the installation process, nodes are shut down and rebooted. These steps guarantee that the
data on disks that are attached to the shared storage bus is not lost or corrupted. This can happen
when multiple nodes try to simultaneously write to the same disk that is not yet protected by the cluster
software.
Use
Table 16
to determine which nodes and storage devices should be presented during each step.
Table 16 Power sequencing for cluster installation
Comments
Storage
Additional
Nodes
Node 1
Step
Verify that all storage devices on the
shared bus are not presented; Power on
all nodes.
Not Presented
On
On
Setting up net-
works
Shut down all nodes. Present the shared
storage, then power on the first node.
Presented
Off
On
Setting up
shared disks (in-
cluding the Qur-
om disk)
Shut down first node, power on next
node. Repeat this process for all cluster
nodes.
Presented
On
Off
Verifying disk
configuration
Shut down all nodes; power on the first
node.
Presented
Off
On
Configuring the
first node
Power on the next node after the first
node is successfully configured. Com-
plete this process for all cluster nodes.
Presented
On
On
Configuring addi-
tional nodes
At this point all cluster nodes should be
on.
Presented
On
On
Post-installation
To configure the Cluster service on the storage system, an account must have administrative permissions
on each node.
Setting up networks
Verify that all network connections are correct, with private network adapters connected to other
private network adapters only, and public network adapters connected to the public network.
Configuring the private network adapter
The following procedures are best practices provided by Microsoft and should be configured on the
private network adapter.
•
On the
General
tab of the private network adapter, ensure that only TCP/IP is selected.
•
Ensure that the
Register this connection's address in DNS
is not selected in the DNS tab under
advanced settings for Internet Protocol (TCP/IP) Properties.
•
In all cases, set static IP addresses for the private network connector.
HP X1000 and X3000 Network Storage System User Guide
95
Содержание StorageWorks X3000
Страница 12: ...12 ...
Страница 22: ...Installing and configuring the storage system 22 ...
Страница 40: ...Storage system component identification 40 ...
Страница 110: ...Troubleshooting servicing and maintenance 110 ...
Страница 118: ...Support and other resources 118 ...
Страница 125: ...French laser notice German laser notice Italian laser notice HP X1000 and X3000 Network Storage System User Guide 125 ...
Страница 132: ...Bulgarian recycling notice Czech recycling notice Danish recycling notice Regulatory compliance notices 132 ...
Страница 134: ...French recycling notice German recycling notice Greek recycling notice Regulatory compliance notices 134 ...
Страница 136: ...Lithuanian recycling notice Polish recycling notice Portuguese recycling notice Regulatory compliance notices 136 ...
Страница 138: ...Swedish recycling notice Battery replacement notices Dutch battery notice Regulatory compliance notices 138 ...
Страница 139: ...French battery notice German battery notice HP X1000 and X3000 Network Storage System User Guide 139 ...
Страница 140: ...Italian battery notice Japanese battery notice Regulatory compliance notices 140 ...
Страница 141: ...Spanish battery notice HP X1000 and X3000 Network Storage System User Guide 141 ...
Страница 142: ...Regulatory compliance notices 142 ...