Prepare the Switch for Installation
The following section describes how to install the mounting hardware that
attaches the switch to the rails. This hardware includes:
■
Two front mounting brackets
■
Two rear mounting plates
■
Eight 10-32, flat-head Phillips screws
Use these steps to secure the mounting hardware to the switch, as shown in
Figure 22
:
1. Locate the two front mounting brackets in the shipping carton.
2. Position the front mounting bracket (
5
) so that the bracket’s angled side faces
out and is on the upper part of switch side.