1.3 Initial Operation
The large display 4985 is delivered in its casing ready for operation. It is now only necessary
to install the connections required for operation.
1.3.1 Opening and Closing of Housing
For installation of the display the right-side panel of the housing needs to be removed. The
right-side panel is fixed into the housing by spring locks.
Opening of housing
a. Pull the right-side panel to the right out of the housing
(ATTENTION: DO NO JAM)
b. When pulling out, override the pressure point of the spring locks
at the top
first and then
at
the bottom
(traction approximately 50N
– corresponding with at driving power of
approximately 5kg)
c. Pull the front panel to the right out of the housing
Pay attention to a secure hold when opening the large display.