3.8 INSTALLATION - ELECTRICAL
WARNING: THIS APPLIANCE MUST BE EARTHED. IT IS SUITABLE FOR A.C. SUPPLY ONLY.
ELECTRICAL INSTALLATION MUST BE CARRIED OUT BY A COMPETENT ELECTRICIAN
AND BE IN ACCORDANCE WITH THE LATEST I.E.E. WIRING REGULATIONS.
ENSURE THE ELECTRICAL SUPPLY IS SWITCHED OFF BEFORE MAKING ANY
CONNECTIONS TO THE ELECTROMAX SOLAR.
Installation of the electrical system requires:
Connection to a 240v 45A supply for the boiler
•
Connection to a 240v 16A for the control panel and boost immersion heater
•
Connection to a 240v 16A off peak supply for the immersion heater
•
Connection to the room thermostat
•
Connection to the solar collector sensor.
•
Connection to the solar divertor valve (if fitted).
•
The electrical supply to the property must be checked to ensure it is of sufficient current rating
and voltage.
The consumer unit must be fitted with a double pole 30mA RCD.
The electric boiler circuit must include a 45A MCB in the circuit.
The immersion heaters must include a 16A MCB in each circuit
Each circuit must incorporate an isolating switch with a contact separation of at least 3mm
in both poles.
Immersion heater, boiler and room thermostat cables must be routed via the cable entry holes
in either the right or left hand side of the upper panel. There are four holes in each side, one
25mm hole and three 20mm holes.
FIGURE 16: CABLE GLANDS
CABLE
GLANDS