7 Commissioning the HDG Euro – Conditions
64
HDG Euro V3.0 with HDG Lambda Control 1 - V 1 - en
©
HDG Bavaria GmbH 06/2008
7 Commissioning the HDG Euro
The HDG Euro will initially be commissioned by specialists from HDG
Bavaria or from an authorised HDG partner.
The commissioning includes an introduction to the operation and
maintenance of the HDG Euro as well as the taking of measurements
on the system for pollution and heating capacity.
7.1 Conditions
The following requirements must be met to ensure there are no
problems during commissioning.
•
The HDG Euro has been filled with water as specified.
•
The HDG Euro has been deaerated.
•
The pressure of the membrane expansion container has been
adapted to on-site conditions.
•
All required DIN EN 12828 safety devices have been installed and
are ready for operation.
•
The supply of power to all components has been provided
(makeshift solutions are not sufficient).
•
The chimney installation corresponds to the legal regulations.
•
All doors and openings on the boiler and on the chimney
connection duct have been checked for a proper seal.
•
Air supply for combustion has been provided.
•
A sufficient amount of fuel is available.
Danger!
Material damage and injury due to incorrect commissioning.
Commissioning the system requires comprehensive specialist
knowledge. If this commissioning is done by an untrained person,
the HDG Euro can be damaged.
Only allow authorised specialists to perform the commissioning.
Содержание Euro V3.0
Страница 1: ...hdg bavaria com HDG Euro V3 0 with HDG Lambda Control 1 Operation Manual V 01 06 2008 ...
Страница 2: ......