7.
s
er
vI
ce
Performance testing GH2 ang GH2 HD
• The performance test provides a first-hand impression
of the status of the entire system . A note is made of any
instances of non-compliance which are subsequently
investigated further during the main inspection .
• The hoist is run through the entire system by the tech-
nician, who makes a general observation of the system
while all system functions are tested .
• Testing of up/down function .
• Testing of drive motor, if any .
• Checking of any undesired noises from the wheels .
• Checking of any undesired noises from the gears/motor .
• Testing of Combi-lock, switch tracks and turntables, if
any .
Main inspection GH2 and GH2 HD
• Remove covers and follow the procedure below, if
necessary together with the electrical functional descrip-
tion for GH2 ang GH2 HD .
• Check transformer min . 24 V AC
• Check voltage from the transformer to the charging
station, including any room-covering charging station,
thereby ensuring that the cable connections are correct .
• Check batteries:
Measure battery voltage on both batteries without load .
It must be above 12 .0V and the difference between
the two batteries must be max . 0 .3V . Now measure the
voltage with load (60-80 kg (132-176 lbs)) . The rate of
speed at which the voltage drops must be the same
on both batteries, and the difference between the two
batteries must be max . 0 .3V .
• Check emergency stop and emergency lowering
function with a load corresponding to 85 kg (187 lbs) .
• Check endstop down – first without load on the lifting
strap . It should not be possible to lower . Then test with
the weight of the lifting hanger on the strap . It should
now be possible to lower .
• Check endstop up . Run lifting strap all the way up and
against the stop . This should cause the micro switch to
stop the lifting function immediately . The same should
apply when the strap is at an angle of more than 45º
relative to the hoist lengthways and 10º crossways .
• Check lifting strap for correct installation and check
for cut threads . If the edges of the strap are very worn
due to swings or if there are any other signs of wear,
the strap should be replaced . Also check the hoist to
identify any sharp edges or burrs . Any defects must
be repaired before fitting of the new strap . Follow the
instructions on the fitting of lifting straps .
• Check trolley – as regards the fitting of the trolley to the
hoist, locking rings must be fitted at either end of the
axle which holds the trolley .
• Check coating if the hoist is coated . It must be ensured
that the coating remains functional . If not, the hoist must
be recoated using Silicone Spray – Sil Slip A .
• Fit covers .
• Carry out performance test of the entire system with
rated load .
Rail system in general
• Carry out a performance test of the entire system with
rated load .
• Check that the system is completely level .
• Check the bracket to ensure it has been correctly
tightened .
• Check rail connections to ensure correct positioning
of cylinder pins and rail connectors .
• Retighten all endstops and check for installing safety
split pin .
• The rail system should be marked with the maximum
load, cf . the distance between the fittings .
Combi-locks
• Function test, including checking the diode function on
the manual control .
• Check transformer, 24 volt AC .
• Check attachment to rail (remove covers) .
• Check that the tongue does not subject the safety lock
on the traverse rail to a maximum load – the safety lock
must not fully open . If this is the case, the Combi-lock
must be adjusted .
• Both safety locks must be checked manually and
electronically – must return normally without problems .
Switch track manual/electrical
• Function testing .
• Check transformer 24 V AC .
Turntable
• Function testing .
• Check transformer 24 V AC .
• Check endstop function – the turntable rail must be
completely in line with rails on either side of the turn-
table . If this is not the case, the rail system must be
adjusted, and if the turntable turns too much, the cover
plates must be removed and the end stop adjusted .
Main inspection of GH2, GH2 HD
and rail system
Содержание GH2
Страница 2: ......
Страница 4: ......
Страница 10: ...Bla bla Guldmann GB 1394 11 08 12 ...
Страница 34: ...Bla bla Guldmann GB 1394 11 08 36 ...
Страница 73: ...Bla bla Guldmann GB 1394 11 08 75 4 electrical connection Interconnection diagram GH2 twin ...
Страница 87: ...Bla bla Guldmann GB 1394 11 08 89 ...
Страница 88: ... Guldmann GB 1394 11 08 90 5 control Control 5 Checkliste 88 ...
Страница 90: ... Guldmann GB 1394 11 08 92 6 toolbox ToolS 6 Overview of tools for rail installation 93 ...
Страница 93: ... Guldmann GB 1394 11 08 95 7 service GH2 Service manual ...
Страница 107: ... Guldmann GB 1394 11 08 109 7 service Periodic Inspection ...
Страница 108: ......
Страница 109: ......