Working Platform
Assembly and Operating Manual
Page 30 of 52
BL 061 U Edition 06.2007
•
Plug in connection line to the limit switch “EMERGENCY STOP”.
Fig. 31 Plug in connection line
9.3.5
Assembling the central control system
•
The central control system is hung on the inside of the platform railing
on the upper railing strut (insert diagonally!).
NOTE:
The suspension on the
longitudinal side
is important for using the control
system for two winches as otherwise the inclination switch-off will not
work!
Fig. 32 Assembling central control system
9.3.6
Connect working platform electrically
For mains connection see Chapter 7
•
Connect mains supply for the lift to the building site main cabinet (plug CEE 5x16 A, 6h, red
with
phase inverter
or a CEE plug 3x16 A, 9h, blue, respectively for the 230V drive unit).
•
Hook the traction relief hose for the mains line to the central control.
Fig. 33 Traction relief
•
Plug CEE plug into the mains line.
ATTENTION
Hang the plug-in connection vertically so that the coupling is located above the plug (risk of water
permeation).