300 Z/ZP 2
Operation
BL144 GB 2019-11
39
4.2
Commissioning
1 Main switch
2 Control light, ready for operation
3 Socket [blue] for ground
control/manual control
4 Socket [red] for electric module
on the landing level doors (or
dummy plug during assembly)
Fig. 7: Ground station switch box
Only with 2.00 m base enclosure with sliding door
5
Socket [grey] for 2 m base enclosure with sliding door (or dummy plug without
this base enclosure)
The connected control of the 2.00 m base enclosure automatically
switches the safety functions (stop and warning signal) for the
lower safety area.
Turn the main switch to the "I" position [ON] .
The green control light (2) lights up for confirmation.
Trolley switch box
Set the key switch (10) to position 0
and remove the key,
Fig. 8: Selector switch for operating
mode, ready for operation
The key has to be removed to prevent incorrect operation during
operation.