Initial Commissioning
Checks before initial commissioning
2007-9015-001
03-2014
6.3
Checks before initial commissioning
The owner should ensure that:
● Each point of the warranty registration form have been met.
● Oil in the hydraulic power unit tank is at proper level.
● 2 ball valves under hydraulic power unit have been opened.
● 2” [5cm] of biodegradable oil is poured above the piston. Refer to section on
Lubricant specifications.
● All personnel who perform work on or with the product must carefully read,
understand and act in accordance with the instructions.
● All stationary components are securely anchored to the floor.
● All grease zerks have been lubricated.
● All guards and covers are in place.
● All installation materials and debris are cleaned up and removed from the
equipment.
● Check the product for visible damage; immediately remove any faults that
are found (note personnel qualification required) or send to the specialist
dealer - the product may only be used if it is perfect condition.
Hydraulic power unit
● Ensure the oil reservoir of the
hydraulic power unit is 2/3 full. Refer
to section on Lubricant
specifications.
Oil sight
gauge
● Ensure 2 ball valves have been opened as shown below.