Chapter 2. Installing the Pipe Nozzles
28
Model T17 Installation Guide
2.3.3 Determining and Marking the Second Nozzle Location - MR1 Mid-Radius (cont.)
6.
The new position for the center of the second nozzle is now identified as the intersection of the mark line on the
strip of film and the second edge of the strip of film (see Figure 36 below). Center punch this location prior to
removing the strip of film.
Figure 36: Center Punch the Second Nozzle Location
7.
Remove the strip of film from the pipe.
8.
Scribe 6” long vertical and horizontal lines on the pipe that intersect at the center punched area, as shown in
below.
Figure 37: Scribe Lines at the Punch Mark
IMPORTANT:
Follow the illustrations and instructions above carefully. Because of the non-symmetrical geometry of
the off-diameter chord in a mid-radius configuration, a mirrored location of the two nozzles with respect
to a plane either perpendicular to or parallel to the pipe in the above illustrations will not accommodate
the nozzles supplied in the standard
Nozzle Installation Kit
(NIK)
.
Mark Line
Punch Here
Second Edge
Overlapping
Area
Содержание T17
Страница 1: ...GE Oil Gas Flow 916 128 Rev D September 2020 Model T17 Ultrasonic Flow Transducer Installation Guide ...
Страница 2: ......
Страница 4: ...ii no content intended for this page ...
Страница 62: ...Chapter 2 Installing the Pipe Nozzles 54 Model T17 Installation Guide no content intended for this page ...
Страница 64: ...Chapter 3 Installing an Isolation Valve 56 Model T17 Installation Guide no content intended for this page ...
Страница 88: ...Chapter 6 Specifications 80 Model T17 Installation Guide no content intended for this page ...
Страница 90: ...Warranty 82 Model T17 Installation Guide no content intended for this page ...
Страница 92: ......
Страница 93: ......