Step 1: Prep the Roof
Follow the sequence below to complete this step.
Step 1a: Prep and Clean the Deck…
For new roofs, start with a clean plywood/OSB deck. For existing
roofs, proceed with a roof tear-off and clear the existing deck of all shingles and underlayment
in the plane of the planned solar array. Remove or hammer in all protruding nails on the deck
and prepare a
smooth and level deck surface
. Sweep away dirt and debris from the roof deck
(
Figure 15
).
Figure 15 Prep and clean the deck
Step 1b: Install Roofing Components on Eaves and Rakes…
Install a drip edge, leak barrier, and starter
roll along the eaves and rakes using industry best practices. Refer to the latest version of the
GAF Steep Slope PRO Field Guide for guidance.
Step 1c: Install Initial Rows of Shingles up to Planned Location of the Starter Bars...
Using the Permit
Design Drawings, determine the number of rows of shingles required between the eave and
the Starter Bars. Locate and mark the lower-left corner of the solar array. The starting point
must always land within the shingle headlap area. For example, in
Figure 16
below, four rows
of shingles are required to reach the starting point.
Step 1a: Prep and Clean the Deck
Step 1b: Install Roofing
Componets on Eves
and Rakes
Step 1c: Install Initial
Rows of Shingles
Step 1d: Install
StormGuard Leak
Barrier Underlayment
Step 1e: Install QuickStart® Peel and Stick Starter Roll
Step 1f: Install VersaShield® SOLO™ Underlayment
Содержание DecoTech
Страница 1: ...P a g e 1 FF GAF Solar Energy System 2019 GAF All Rights Reserved Version 3 1 08 2019 ...
Страница 40: ...P a g e 40 Peel the MLPE Bar Code Affix the Bar Code to the MLPE Map Figure 43 Create MLPE Map ...
Страница 55: ...P a g e 55 SECTION 7 APPENDIX GAF Solar Module Technical Data Table 4 Solaria Laminate Specifications ...
Страница 56: ...P a g e 56 Table 5 Silfab Laminate Specifications ...