Step 2: Build the Starter Bars and the Solar Module Assemblies
Follow the sequence below to complete this step.
Step 2a: Assemble the Starter Bars...
Each Starter Bar receives 3-5 Adjustable Feet Bases (check the
approved system drawings for your installation) which are attached using the provided
carriage bolts (5/16"-18 x 1" Steel, Zinc Plated) and nuts (Flanged, 0.313''-18, Steel, Zinc
Plated). The tooth grooves of the Adjustable Foot Base should align with the tooth groves of
the Starter Bar. Use the factory-assembled position of the Adjustable Foot (above the second
tooth) by default. Torque the nut to 75 inch-pounds (8.5 Nm) See
Figure 21
below. Note
that adjacent Starter Bars share a common foot as shown in
Figure 22
below. Please refer to
the Permit Design Drawings for the Starter Bar arrangement.
Step 2a: Assemble the Starter Bars
Step 2b: Install the Adjustable Feet
Step 2c: Install the MLPE Brackets
Step 2d: Install the WEEB® Lug and
MLPE
Step 2e: Connect the PV Wires
Step 2f: Ensure Proper Wire
Management
Default height
of the
adjustable foot
base is to
expose 2 tooth
grooves
Adjustable
foot base
Starter Bar
Carriage
Bolt
Nut
Figure 21 Assembling the Starter Bar
Содержание DecoTech
Страница 1: ...P a g e 1 FF GAF Solar Energy System 2019 GAF All Rights Reserved Version 3 1 08 2019 ...
Страница 40: ...P a g e 40 Peel the MLPE Bar Code Affix the Bar Code to the MLPE Map Figure 43 Create MLPE Map ...
Страница 55: ...P a g e 55 SECTION 7 APPENDIX GAF Solar Module Technical Data Table 4 Solaria Laminate Specifications ...
Страница 56: ...P a g e 56 Table 5 Silfab Laminate Specifications ...