Maintenance Instructions
11.3.11
Panda PMS 8.000 NE - 42 NE Manual.R05 - Kapitel/Chapter 6: Maintenance Instructions Seite/Page 127
Fig. 6.12.0-2: Ventilating Screw
Open the ventilating screw above the cooling water pump
casing.
Sample Picture
Fig. 6.12.0-3: Ventilating Screw on the Thermostat Housing
Open the ventilating screw on the thermostat casing.
Sample Picture
Fig. 6.12.0-4: Cooling Water Expansion Tank
The cooling water can be filled into the External expension
tank.
If the cooling water level no longer drops (the cooling water
level in cold waters must cover the tin in the exhaust elbow),
close the filler cover and the cooling water screws and then
start the generator.
Run the generator for approx. 60 seconds, then switch off
Refill cooling water via the compensation tank.
The external compensation tank should be filled to a max 20%
in a cold state. It is very important that a larger expansion area
is maintained above the cooling water level.
Repeat this procedure several times.
If there is no change to the state of the cooling water level, the generator is re-started for 5 minutes. Thereafter the
de-aeration must be repeated two to three times.
It might be advisable to repeat the venting procedure a couple of days later, to ensure that all air that may have
remained in the system is finally released.
10
10
Содержание 10000 NE
Страница 26: ...Seite Page 26 General R01 1 11 3 11 Leere Seite Intentionally blank General References and Regulations...
Страница 162: ...Seite Page 162 Panda PMS 8 000 NE 42 NE Manual R05 11 3 11 Leere Seite Intentionally blank Generator Faults...
Страница 208: ...Seite Page 208 Panel Generator Control P6 RE0703_Kunde_eng R06 1 11 3 11 Leere Seite Intentionally blank Measurements...