8.9 Procedure for dismantling the equipment
WARNING –
B
The dismantling operations must be carried out with the equipment disconnected from any voltage sources. Refer
to
“Inverter total de-energization and safe access”
paragraph on this manual to know all the necessary step to safely operate
on the inverter.
ATTENTION –
A
Never open the power module
(01)
or wiring box
(02)
in the case of rain, snow or a level of humidity >95%. Always
carefully seal all unused openings.
Even though the device is equipped with an anti-condensation valve, air with extremely high levels of humidity can lead to the creation of
condensation inside the inverter.
As the inverter is almost completely insulated from the outside, condensation can also form after maintenance interventions in certain
weather conditions.
ATTENTION –
A
During dismantling always protect the inverter parts that are installed and exposed to the weather elements!
ATTENTION –
A
Staff authorised to carry out the dismantling operations must be specialised and experienced in this job. They must
also have received suitable training on equipment of this type.
The inverter consists of an power module
(01)
, a wiring box
(02)
and a mounting bracket
(03)
which may be dismantled separately.
To dismantling and disassemble the power module (01) follow these steps:
• Disconnect any external voltage sources and isolate the equiment referring to the
“Inverter total de-energization and safe access”
paragraph.
• Disconnect all internal connectors between power module
(01)
and wiring box
(02)
reffering to
paragraph (Follow the indications for connection procedure but in the reverse order).
• Disjoint the power module
(01)
and wiring box
(02)
enclosures reffering to
paragraph (Follow the
indications for the mounting procedure but in the reverse order).
• Lift and remove the power module
(01)
following the indications for the mounting procedure in the
paragraph in the reverse order and the indication for lifting methods in
paragraph.
ATTENTION –
A
Never leave the power module
(01)
or the wiring box
(02)
disassembled on the field. In case is necessary to
disassemble the power module
(01)
only, a IP65 protection covers for wiring box openings (for temporary installation of wiring box
only) kit is available as accessory options.
To dismantling and disassemble the wiring box (02) follow these steps:
• Remove the power module
(01)
as previously described.
• Remove AC cables and protective earth clable.
• Remove any signal cables.
• Remove the wiring box
(02)
following the indications for the mounting procedure in the
“Assembly the Inverter to the bracket”
paragraph in the reverse order and the indication for lifting methods in
paragraph.
To dismantling and disassemble the mounting bracket
(03)
follow the indications for the mounting procedure in the
paragraph in the reverse order.