2.3 Commissioning the CP system on the INTERBUS
PLEASE NOTE
The switching-on instructions in the manual for the
INTERBUS module must also be observed.
Proceed as follows:
1. Connect the INTERBUS cables to the field bus
node.
2. Switch on the operating voltages:
•
for all remote bus/installation remote bus slaves,
•
for the CP system.
3. Switch on the operating voltage for the master
module.
When you switch your controller on, it will automatically
carry out a comparison between the NOMINAL and AC-
TUAL configurations. For this configuration run it is im-
portant that:
Configura-
tion run
– the specifications for the NOMINAL configuration are
complete and correct.
– the power supplies to the PLC and to the field bus
slaves are switched on either simultaneously or in
the sequence specified above.
The bus is not able to operate until all the bus slaves
are switched on.
2. Commissioning
CP FB6-E 9809c
2-17
Содержание Compact Performance CP-FB6-E
Страница 1: ...Compact Performance CP fieldbus node 6 Programming and diagnosis Fieldbus protocol INTERBUS...
Страница 11: ...Contents and general safety instructions X CP FB6 E 9809c...
Страница 12: ...Chapter 1 Installation 1 Installation CP FB6 E 9809c 1 1...
Страница 29: ...1 Installation 1 18 CP FB6 E 9809c...
Страница 30: ...Chapter 2 Commissioning 2 Commissioning CP FB6 E 9809c 2 1...
Страница 58: ...Chapter 3 Diagnosis 3 Diagnosis CP FB6 E 9809c 3 1...
Страница 70: ...Appendix A Technical appendix A Technical appendix CP FB6 E 9808c A 1...