Chapter 4 System Commission 27
DataMate 3000 Series Air Conditioner User Manual
Chapter 4 System Commission
4.1 Inspection Before/After Start-up
1. Face plate
No damage, well insulated and clean
2. Filter
Installed reliably, no damage and clean.
3. Power supply
Measure and record phase-to-phase voltage before system is powered.
Power supply cables are connected reliably.
4. Fan
The rotation is correct after system starts up.
No obstruction material such as cables, tubes, etc. in the discharge area.
The rated current of the fan motor is recorded.
The actual current of the fan motor is recorded.
5. Humidifier (if applicable)
Water supply line is connected. Water level sensor is installed reliably. Drain line is
connected.
6. Heater (if applicable)
Heating components are reliable.
The heater current is recorded.
7. Condenser
The condenser location complies with the requirement. Pipeline is supported and
pitched properly. The trap is installed in a correct position.
8. Others
The user’s setpoints are recorded.
Return air temperature, suction pressure, head pressure, compressor current and
discharge air temperature are recorded.