7
Section 3: General
User Instructions
MAN-02-04-60-0351-EN Rev. 3
February 2019
General
3.8
Delivery Condition of the Actuators
For each actuator, an inspection report is generated upon final inspection. In particular, this
comprises a full visual inspection, calibration of the torque measurement in connection
with an extensive run examination and a functional test of the microcontrollers.
These inspections are conducted and documented according to the quality system and can
be made available if necessary.
The basic setting of the end position must be performed after assembly on the actuator.
CAUTION
Commissioning instructions (see Section 5, page 25) must be strictly observed!
During assembly of the supplied valves at the factory, end postions are set and
documented by attaching a label (see Bild 16). During commissioning at the plant,
these settings must be verified.
3.9
Information Notice (Tag)
Each actuator is provided with a bilingual tag containing key information, which is attached
to the handwheel after final inspection. This tag also shows the internal commission
registration number (see Figure 5).
Figure 5
Tag