WATER TESTING THE INNI
After assembly you need to water test the assembled INNI for any leaks. The INNI should
be tested before installation and after waterproofing the shower floor to ensure that any
problems are addressed before tile installation.
a
Insert Test Ball:
Coat the test ball with Silicone Grease. Place the Test Ball into the Drain Outlet to
create a temporary watertight seal.
b
Block and Level the Drain:
Support the INNI on blocks and make sure it’s level.
c
Fill with Water and Look for Leaks:
Completely fill the INNI with water and verify that there are no
leaks. Best practice is to leave the INNI filled for a minimum of one hour. If any leaks are found,
repair leaking areas with ABS cement. Repeat until there are no leaks. Remove Test Ball before
installation.