Commissioning and System Handover
Commissioning
The walk test feature has been provided to facilitate the commis-
sioning of the system . See
Walk Test Mode
on page 26
The commissioning of the system should be conducted in accor-
dance to BS5839 part 1 Annex H .
The commissioning certificate must be completed and any vari-
ances noted .
The system configuration and variances should be recorded on the
log book .
System Handover
The following documents must be handed over to the Premises
Management of the installation:
•
Zone map
•
Commissioning certificate
•
Log book
•
User Manual
The Premises Management must be demonstrated the operation
of the system and give basic training on the operation of the
system and filling in the log book .
Maintenance
Daily Testing
To be conducted by the Premises Management .
Check that the panel shows no fire or fault indications .
If there are any fault conditions indicated then refer to
Status
Indications
on page 7 to identify the problem .
Weekly Testing
To be conducted by the Premises Management .
• Each week perform a Lamp Test to check that all visual and
audible indicators on the panel are functioning correctly . See
Lamp Test
on page 25 .
• Each week a different zone should be tested . Testing with a
manual call point is the simplest method as these can be easily
triggered with the key provided . Testing with a fire detection
device is more complex as it requires specialist equipment and
may not be possible for all premises . At a minimum a different
manual call point should be tested each week .
• Place the zone to be tested into test mode using the Individual
Zone Test function . See Individual Zone Test on page 25
• Record the weekly test results in the log book .
Quarterly Testing
To be conducted by the Competent Person .
•
Check all previous log book entries and verify that any correc-
tive actions had been taken .
•
Carry out the weekly test and record the results in the log
book .
•
Visually inspect the batteries and their connections .
•
Disconnect the mains supply and check that the fire system is
capable of supplying the fire alarm devices by operating a call
point .
Yearly Testing
To be conducted by the Competent Person .
•
Carry out the weekly test and record the results in the log
book .
•
Carry out the Quarterly testing .
•
Test
ALL
fire detection devices and manual call points .