Installation
Eaton
®
Power Xpert
®
9395C UPS Installation and Operation Manual P-164000821—Rev 01
www.eaton.com/powerquality
4-7
4.3
Mechanically Joining the Sections
1.
Using a forklift, move the PM section to the final installed location.
2.
Remove one top screw and two bottom screws securing the PM section wireway panel (see Figure 4-5).
Lift the panel straight up to remove it from the panel hanger brackets at the top of the cabinet.
3.
Remove the screws securing the top and bottom internal safety shield panels and remove the panels.
Retain the hardware for later use.
Figure 4-5. Section Joining
CAUTION
Use care during installation to protect components mounted on the right side of the ISBM section
and the intercabinet wiring harnesses attached to the left side PM section from damage.
NOTE
The following procedure permits the UPS sections to be installed in a location
where there is limited space to slide the sections together from the sides.
NOTE
For the following steps, verify that the forklift or pallet jack is rated to handle the
weight of the section (see Table 3-1 for cabinet weight).
Wireway Panel
ISBM Section
Содержание 9395C-1000/1000
Страница 2: ......
Страница 23: ...Section I Installation ...
Страница 24: ......
Страница 93: ...Section II Operation ...
Страница 94: ......
Страница 155: ......
Страница 156: ... P 164000821 1 P 164000821 1 ...