Installation
Eaton
®
Power Xpert
®
9395C UPS Installation and Operation Manual P-164000821—Rev 01
www.eaton.com/powerquality
4-11
and P60 connectors attached. Remove the wire ties securing the harnesses and carefully remove the
harnesses from the protective cage. If necessary, loosen the screws securing the protective cage.
13. Locate the mating P50 connector in the PM section wireway (see Figure 4-10) and connect the P50
connector to the J50 connector.
14. Locate the mating P51 connector in the PM section wireway (see Figure 4-10) and connect the P51
connector to the J51 connector.
15. Locate the mating P56 connector in the PM section wireway (see Figure 4-10) and connect the J56
connector to the J56 connector.
16. Locate the mating J60 connector in the PM section wireway (see Figure 4-10) and connect the J60
connector to the P60 connector.
17. Locate the mating P61 connector in the PM section wireway (see Figure 4-10) and connect the P61
connector to the J61 connector.
18. In the PM section (see Figure 4-10), locate the coiled RJ-45 CAN cable. Remove the wire ties securing the
cable to the interior left side panel of the PM section. Route this cable through the round wiring access in
the right side panel of the ISBM section (see Figure 4-10).
19. In the ISBM section, locate the J39 inverter CAN connector on the Pl1 interface board and connect the
RJ-45 CAN cable connector to the J39 connector (see Figure 4-10 and Figure 4-11).
20. Dress the interface harnesses and secure in place with wire ties as necessary to prevent wire damage.
21. When all wiring is complete, reinstall the safety shield panels removed in previous steps.
22. Reinstall the front wireway panel.
Содержание 9395C-1000/1000
Страница 2: ......
Страница 23: ...Section I Installation ...
Страница 24: ......
Страница 93: ...Section II Operation ...
Страница 94: ......
Страница 155: ......
Страница 156: ... P 164000821 1 P 164000821 1 ...