Understanding UPS Operation
Eaton
®
Power Xpert
®
9395C UPS Installation and Operation Manual P-164000821—Rev 01
www.eaton.com/powerquality
6-7
4.
Turn key K-LB to unlock the LBB breaker. Close the LBB breaker.
6.2.8
Transfer to Maintenance Bypass and Load Bank Sequence
Key Operation: Transfer UPS system from Load Bank
1.
Open the LBB breaker. Turn key K-LB and remove from the LBB breaker lock and insert it into the MIB
lock.
2.
Verify key K-ML is in the LBB breaker lock. If not present, remove key K-ML from one of the other Load
Bank breakers common to the system Load Bank and insert into the LBB lock.
NOTE
Multiple systems share a common load bank. A single K-ML key is used to prevent
more than one system from being connected to the load bank at a time. Key K-ML
must be inserted in the Load Bank breaker lock of the system to be connected to
the load bank.
Содержание 9395C-1000/1000
Страница 2: ......
Страница 23: ...Section I Installation ...
Страница 24: ......
Страница 93: ...Section II Operation ...
Страница 94: ......
Страница 155: ......
Страница 156: ... P 164000821 1 P 164000821 1 ...