Project Planning
The following is a typical program and timetable for an installation project, once the
initial order has been received:
1. Project Meeting
Installer and user to be present; system specifications, schematic diagram and
proposed circuit drawing to be available . CF2000 Installation & Commissioning Guide
to be provided .
2. Equipment Fix
Typically 2 week's notice is required for equipment to be delivered . Cable to be
installed and bases/back boxes to be fitted . Then fire sensors, call points, alarm
sounders and interface units can installed .
3. Address Schedule
Schedule of sensor locations to be completed by installer and returned to enable
System programming .
4. Auto Learn
Fire panel panels to be installed and terminated . System to be powered up by
installer and auto learn mode activated (see Auto Learn section) . System to be tested
and verified by installer, prior to final commissioning .
5. Final Commissioning
Minimum 2 weeks notice is required from receipt of Address Schedule and
Commission request form for an Eaton Fire Systems Service Engineer to attend
site to implement/oversee the final commissioning procedures (see Commissioning
section), in conjunction with the installer .