JT1220 Mach 1 Operator’s Manual
Conduct a Bore - 97
Add Pipe
CMW
Add Pipe
1.
Press top of drilling unit throttle switch until engine is at full throttle.
2.
Enable automated pipeloader system (automated pipeloader control only). See “Enable Automated
Pipeloader System” on page 96.
3.
Break joint at saver sub.
4.
Load pipe.
IMPORTANT: If gripper switch is not in the grip position when using optional pipeloader automation,
grippers will open when automation is stopped and gripped pipe could be dropped. To return a dropped
pipe to the drill string, see “Correct Dropped Pipe” on page 135.
Manual Pipeloader Controls
Automated Pipeloader Control
•
Clamp pipe joint. See “Clamp Pipe” on
page 92.
•
Locate drill head.
•
Engage front wrench until pipe is clamped
and pressure develops.
•
Slowly rotate spindle counterclockwise.
Carriage will move back automatically as
threads unscrew.
•
After threads are fully unscrewed, stop
rotation and move carriage to back of
frame.
•
Clamp pipe joint. See “Clamp Pipe” on
page 92.
•
Locate drill head.
•
Engage front wrench until pipe is clamped
and pressure develops.
•
Slowly rotate spindle counterclockwise.
Carriage will move back automatically as
threads unscrew.
•
After threads are fully unscrewed, stop
rotation and move carriage to back of
frame.
•
While carriage is moving, green control
cycle light will come on. Grippers will grip,
pipe will be lubed, and then green control
cycle light will flash.
Manual Pipeloader Controls
Automated Pipeloader Control
•
Make sure lift arms are completely
lowered.
•
Close grippers.
•
Lube upper pipe threads.
•
Move pipe to spindle and lube lower
threads.
•
Raise pipe in box.
•
When carriage is moved to back of drill
frame, press resume switch. Green control
cycle light will come on.
•
Pipe will be moved to spindle, front
threads will be lubed, pipe in box will be
lifted, and then green control cycle light
will flash.
Содержание JT1220 Mach 1
Страница 1: ...JT1220 Mach 1 Issue 2 1 Operator s Manual 054 114 CMW...
Страница 19: ...Safety 18 JT1220 Mach 1 Operator s Manual Emergency Procedures CMW...
Страница 75: ...Prepare 74 JT1220 Mach 1 Operator s Manual Check Supplies and Prepare Equipment CMW...
Страница 107: ...Conduct a Bore 106 JT1220 Mach 1 Operator s Manual Remove Pullback Device CMW...