Electrical installation
Installer reference guide
147
ERRA08~12E + ELVH/23E
Daikin Altherma 3 R MT F
4P708474-1 – 2023.05
A
1
2
4
5
S6S
S7S
S8S
S9S
3
B
A
B
A8P
X801M
a
1 2 3 4 5
a
Installation of EKRP1AHTA is required.
4
Fix the cable with cable ties to the cable tie mountings.
9.3.10 To connect the safety thermostat (normally closed contact)
Wires: 2×0.75 mm²
Maximum length: 50 m
Safety thermostat contact: 16 V DC detection (voltage supplied by PCB).
The voltage-free contact shall ensure the minimum applicable load of
15 V DC, 10 mA.
—
1
Open the following (see
"7.2.6 To open the indoor unit"
1
Top panel
1
2
3
2
User interface panel
3
Upper switch box cover
2
Open the service cover. See
"7.2.2 To open the outdoor unit"
3
Connect the safety thermostat (normally closed) cable to the appropriate
terminals as shown in the illustration below.
Note:
The jumper wire (factory-mounted) must be removed from the respective
terminals.