73
FieldSmart
®
Fiber Active Cabinet (FAC) 900
__________________________________________________________
Installation Manual
Direct: 763.476.6866 • National: 800.422.2537 • www.SeeClearfield.com • [email protected]
Manual 020420 REV B - April 2019
Step 8:
Step 9:
Step 10:
Step 11:
To install the EXM, do the following:
a.
Repeat steps 1–3 above.
b.
Slowly lower the EXM onto the mounting brackets, and position it against the FAC 900 wall, aligning the
mounting holes on the base on the EXM with the mounting holes in the mounting brackets.
Note:
If properly aligned, the entry duct in the EXM should slide down over the conduits protruding up from the
conduit assembly as the EXM lowers. If necessary, reach down through the entry duct to grasp and align the
conduit to guide it through the entry duct. Do not reach under the EXM.
c.
Pull the earth ground wire into the compartment through the cable entry box.
d.
Before removing the lifting device, from inside the EXM, loosely install (2) 1/2”-13 x 1.25” hex screws
through holes at each end of the EXM base and the counterpart holes in the mounting brackets to prevent the
enclosure from slipping off the brackets.
e.
Remove the lifting device from the EXM.
Attach the EXM to the FAC 900 cabinet as follows:
a.
Get the six shoulder screws, six flat washers and six lock washers (provided with the EXM installation kit).
b.
From inside the EXM, install one screw, lock washer and flat washer in the mounting holes on the EXM wall,
and into corresponding threaded nut on the FAC 900 compartment wall.
c.
Tighten the screws to secure the EXM to the FAC 900, ensuring that the EXM gasket is compressed around
the entire perimeter of the gasket for a water tight seal.
Remove the right-side lifting detail from the FAC 900 and EXM, as required:
a.
Remove the (3) bolts securing the lifting detail to the enclosure.
b.
Remove the lifting detail, and set aside hardware.
Install the stabilizer brackets. Refer to Installing the Stabilizer Bracket(s) for instructions.