Cisco 7600 Series Router Installation Guide
OL-4503-26
Chapter 5 Removal and Replacement Procedures
Removing and Replacing the Power Supply
xxxx
Installing a WS-CDC-2500W Power Supply in a Cisco 7609 Router
Warning
Before performing any of the following procedures, ensure that power is removed from the DC circuit.
Follow these steps to install a DC-input power supply:
Step 1
Ensure that the system (earth) ground connection has been made. For ground connection installation
instructions, see the
“System Ground Connection” section on page 3-19
.
Step 2
Verify that power is off to the DC circuit that is connected to the power supply you are installing.
Caution
Use both hands to install and remove power supplies. Each DC-input power supply weighs between 22
pounds (9.9 kg) and 33 pounds (15 kg).
Step 3
Grasp the power supply handle with one hand, and place your other hand underneath the power supply.
Slide the power supply into the power supply bay. Make sure that the power supply is fully seated in the
bay (
Figure 5-69
).
Figure 5-69
Handling a DC-Input Power Supply
Step 4
Tighten the power supply captive installation screws. (See
Figure 5-70
.)
INPUT
OK
FAN
OK
OUTPUT
FAIL
I
0