REFERENCE
EDMS NO.
REV.
VALIDITY
TOF-TAR-PRD-0001
1867100
1.0
RELEASED
Page 58 of 93
Name of task
410. Remove ladders
and equipment and
prepare for the removal
of the block
Exposed people
Local dose rate
10 µSv/hr
Workforce
3 people
Time needed
15 min
Calculated dose
Responsible
EN-STI
Involved
EN-EA/ EN-HE/ HSE-RP/ EN-CV
Comments:
Everything should be checked before moving on from
this stage, as afterwards the target will be exposed.
HSE-RP suggests that since this is a critical point in
the operation, a "clearance" meeting should be
organized with all the stakeholders (EN-STI, EN-HE,
HSE-RP, EN-CV, EN-EA, etc.) to verify and get the
green light to proceed further.
A manual winch will be needed to recover persons in
the case of an emergency.
Содержание ATOMTEX BDKG-24
Страница 62: ...REFERENCE EDMS NO REV VALIDITY TOF TAR PRD 0001 1867100 1 0 RELEASED Page 62 of 93...
Страница 65: ...REFERENCE EDMS NO REV VALIDITY TOF TAR PRD 0001 1867100 1 0 RELEASED Page 65 of 93...
Страница 68: ...REFERENCE EDMS NO REV VALIDITY TOF TAR PRD 0001 1867100 1 0 RELEASED Page 68 of 93...
Страница 73: ...REFERENCE EDMS NO REV VALIDITY TOF TAR PRD 0001 1867100 1 0 RELEASED Page 73 of 93...