Placing the heating system in operation
Logano GB125 BE US/CA - Technical specifications are subject to change without prior notice.
37
6.9
Commissioning log
V
Initial and date the commissioning operations carried
out.
Commissioning operations
Page
Readings taken
Comments
1.
Fill heating system and check for leaks
26
____________ psi
– Heating system pressure
2.
Fill trap with water
3.
Bringing the system up to operating pressure
V
Bleeding heating system
V
Testing relief valve
V
Adjust the expansion vessel pressure (
Æ
expansion vessel doc-
umentation)
33
____________ psi
4.
Checking combustion air supply and flue system
5.
Checking position of heat exchanger baffles
34
6.
Documentation
34
7.
Start up the burner (
Æ
burner documentation)
34
8.
Checking the manual reset high limit (STB)
36
9.
Adjust the programming unit settings to suit the customer's
requirements (
Æ
programming unit documentation)
10. Inform operator, hand over technical documentation
Confirmation of properly completed commissioning
Company stamp/signature/date
Tab. 14
Inform the customer about the correct fuel
and correct operating pressure. Enter the de-
tails in the table (
Æ
boiler operating instruc-
tions).