Placing the Boiler in Operation
8
Logano G125 BE - Specifications subject to change without notice.
46
8.11 Detailed Start-up Procedure
z
Check off performed start-up steps, sign and date.
Start-up Procedure
Page
Value Measured
Comments
1.
Filling of system and check for leaks
33
__________ psi
2.
Set operating pressure
Vent heating system
Check operation of relief valve
Pre-set expansion tank pressure (
Î
see expansion tank manufacturer in-
structions)
39
__________ psi
3.
Check combustion air and venting system
4.
Check position of flue baffles
40
5.
Turn on control (
Î
Refer to control Service Manual)
41
6.
Turn on burner (
Î
Refer to burner Service Manual)
41
7.
Measure stack temperature (Adjust if needed)
42
__________ °F
8.
Check manual reset high limit (STB)
44
9.
Adjust control settings based on requirements (
Î
Refer to control Service
Manual)
10. Inform end user and hand over instructions
Confirm start-up procedure
Company stamp/signature/date
NOTICE
z
Always inform your customer regard-
ing proper fuel source and record in
Î
Operating Manual.