5 | Installation
Büchi Labortechnik AG
24/100
Operation Manual Lyovapor™ L-200/L-200 Pro
5
Installation
5.1
Installation site
NOTICE
Instrument damaged if switched on too early.
After transporting, wait twelve hours before switching on the instrument. The fluid
in the cooling system requires twelve hours to collect in the refrigerant compressor.
The installation site must meet the following requirements:
Firm, level surface
Minimum space requirement: 520 mm x 645 mm x 510 mm (W x D x H).
Take into account the maximum product dimensions and weight.
Take into account the 1100 mm operating height of the drying attachments.
Clearance on each side of the instrument must be at least 30 cm. This clearance
ensures air circulation and prevents the instrument from overheating.
Do not place loose papers or cloths below or to the sides of the instrument, as
these could impede the air circulation if drawn in.
Operate the instrument at an ambient temperature of +15°C to +30°C.
Do not expose the instrument to any external thermal loads, such as direct solar
radiation.
When installing the instrument, make sure that the feet do not bend.
When mounting on an instrument cart, place the feet of the instrument into the
supports on the instrument cart.
NOTE
Make sure that the power supply can be interrupted at any time during an
emergency.
5.2
Securing against earthquakes
The Lyovapor™ L-200 has an earthquake fixing point to protect the device against
falling.