June 2021
Installation, Operation and Maintenance Manual
MAN712 Rev. 9
Section 12: Battery Maintenance and First Installation
Battery Maintenance and First Installation
112
15. Connect the 3 wires connector of the Default Battery Pack to CN2 of the Process
Card and fasten its screws.
Figure 42
16.
Verify the date of the ELBS-20. If it is not the present one, set it to the right value.
17.
Launch the “Update Battery Maintenance Command verify that the status of the
used Battery Packs is “OK” (see Sections 6 and 7) and that the “Next. Batt. Maint.”
parameter is correctly updated (see Sections 6 and 7).
18.
Close the cabinet of the ELBS-20 (8 mm Allen key for the EJB51 cabinet).
19.
Enter the desired Operating Mode of the ELBS-20 (see Sections 6 and 7).