5 Assembly in-roof system
In-roof System
Page 42 / 64
EN141217 Axitec GmbH, Otto-Lilienthal-Str. 5, 71034 Böblingen, Germany, +49 (0)7031 62 88-5186
PIC 5-9:Example laying sequence
NOTE
Ensure that the continuous connection cable and connection
cable were laid before the mounting of the modules.
Lay out the module connection cables to the left before placing
the modules in position so that the subsequent module in the
series can be reached.
1.
Place the first photovoltaic module in position to the right in the
lowest row in the mounting bracket. Make sure that the drainage
channels of the frame profile are to the left, and the free laminate
edges to the bottom.
2.
Place the edge connection profile and if necessary connecting plates
right in position with the frame profiles at the field edge in the
bracket.