Installation
35
12AWFSL
If two jacks are not in the same level after
above bleeding procedure, it’s possible to level
them by bleeding the jack P1 (the slave jack on
the runway P1) in the following way:
• Place the jack P1 at approximate .4” height
(make the cylinder stroke at approximate
2”)
• Loosen the bleeding plug (ref. Fig.20) on
the cylinder to let trapped air escape
• Re-tighten the plug after trapped air is
escaped.
After bleeding of the lift, make sure to close all leveling cocks.
Lift cannot be lifted if leveling cocks are opened.
7.9
Anchoring And Runway Adjustment
To make an alignment of motor-vehicle, two runways should be perfectly leveled
and be in the same height when resting on safeties.
For the proper adjustment of leveling accuracy proceed as follows:
• Raise the runways (without the vehicle)
up to a height of about 3 feet (normal
height for wheel alignment). Make sure
two runways are in the same position
when resting the safeties.
• Using the bases as guide, drill each
hole in the concrete approximately 5
inches deep with the rotary hammer
drill 16mm To assure full holding power,
do not ream the hole or allow drill to
wobble.
• After drilling, remove dust thoroughly
from each hole using compressed air or
wire brush.
• Assemble the washers and nuts on the anchors then tap into each hole
with a hammer until the washer rests against the bases.
Содержание 12AWFSL
Страница 1: ...Replace This With Cover PDF ...
Страница 16: ...Technical Specification 16 12AWFSL Figure 3A Layout For In Ground Installation ...
Страница 17: ...Technical Specification 17 12AWFSL Figure 3B Layout For On Ground Installation ...
Страница 21: ...Technical Specification 21 12AWFSL Figure 6 Electrical Plan 220V 1Ph ...