28
1) Determine the flue terminal installation
location and make a 160 mm diameter hole.
Install the sleeve into the hole with the
triangular mark ( ) pointing up. Use the
wall anchors and rounded wood screws.
174
142
142
174
Screw holes (4)
(7.2 mm diameter and
35 to 40 mm depth).
Triangular mark ( )
Before installing the sleeve, adjust its length to fit
the wall thickness.
(The length can be adjusted in increments of 10 mm.)
Waterproof the clearance between the sleeve
and wall hole with a high temperature sealant.
2) Attach the wall flange to the sleeve.
Sleeve
Wall flange
Tapping screw
Terminal Orientation Flange Orientation
Outlet Orientation
(1)
The terminal cannot be installed in this
orientation.
Sleeve
Waterproof the
clearance with a high
temperature sealant.
Rounded wood screw (short)
Sleeve
Wall anchor
Waterproof the clearance with
a high temperature sealant.
Rounded wood
screw (long)
(2)
(4)
(3)
Up
Down
Up
Down
Top
Bottom
Correct
Correct
Incorrect
Incorrect
Intake
Exhaust
Intake
Exhaust
Up
Down
Up
Down
Intake
Exhaust
Intake
Exhaust
174 mm
210 mm
174 mm
210 mm
174 mm
210 mm
* The proper flange orientation
depends on the desired
orientation of the flue terminal.
* Unless the flue terminal is
installed as in option (1) in the
chart to the right, the outlet will
need to be adjusted in order to
ensure it is oriented in the proper
direction.
Remove this screw
and slide out the
external cylinder.
Slide out the external cylinder
until it is flush with the external
wall and replace screw.
160 mm dia.
15-1-4. Flue Terminal Installation Procedure
* When drilling, take care not to damage electric
wiring, or gas or water piping in walls.
(L)WH42̲56(25̲32)̲E
05.10.4, 1:35 PM
28