16

W1

B. Running current  

transformer tails

1.  Run CT conduit from Solshare to main switchboard 

(the CT conduit gland is the pre-installed CT conduit 

gland on the underside of the SolShare - see the 

underside view diagram on p. 13 to ascertain wher

the CT conduit gland is).

2.  Look for labels on current transformers and current 

transformer tails. Ensure these match the  

corresponding tenancy.

3.  Run tails of CTs from main switchboard to SolShare 

through conduit.

Electricity Meter panel

Unit main switches

X X X X X X

M1

X X X X X X

M2

X X X X X X

M3

X X X X X X

M4

6

5

4

3

2

1

7 8 9 10 11 12 13 14 15

X X X X X X

M5

X X X X X X

M6

X X X X X X

M7

X X X X X X

M8

X X X X X X

M9

X X X X X X

M10

X X X X X X

M11

X X X X X X

M12

X X X X X X

M13

X X X X X X

M14

X X X X X X

M15

Area of focus:  

Conduit cable

Current transformers to SolShare connections

Wiring tails to Solshare:
1. Connect the CT cabling to the CT connector  

block, as per the diagram to the right. To do this: 

- Push the orange tab in and hold. 

- Feed the CT cable into the hole. 

- Once inserted, release the orange tab. 

- Confirm cable is secure by giving it a gentle tug.

2. Repeat for all CT cables of the red phase.
3. Repeat steps 1 & 2 for white and blue phase 

connector blocks.

4. Plug each CT connector block into the  

corresponding socket of the SolShare.

Important: 

Make sure colours and orientation of connectors 

are identical to the image above. To ensure you 

are positioning them correctly, check that the  

orange tabs are above your plugged in cables,  

and labels read as above.

W1

W2

W3

W4

W5

1-

1+

2-

2+

3-

3+

4-

4+

5-

5+

1-

1+

2-

2+

3-

3+

4-

4+

5-

5+

Important

If you are using the standard 75A CTs provided 

with the SolShare, their 10m tails cannot be 

extended.
If you require tail lengths of more than 10m,  

an additional upgraded CT set should have 

been ordered at the time of ordering the 

SolShare. Please call Allume on the phone 

number provided on the back page of this  

manual to order the upgraded CT kit.

Important

The SolShare has come with a CT connection 

aid. Place the CT connecter into the connection 

aid to help with the termination of the CT tails.

Important

If you are using the upgraded CT set, these come with 10m tails but can be extended to a total of up to 50m.  

The tail extension can be done for each CT separately using the following recommended parts:
-  Butt splice connector (appropriate size for cable)
-  Twisted shield cable, minimum 24 AWG size (to the length required on top of 10m to make the run  

between SolShare and main switchboard)

CT 

CONNECTION 

AID

CT CONNECTOR 

BLOCK

Содержание SolShare SOLSHARE-3P-35A-03

Страница 1: ...1 SolShare Installation Manual...

Страница 2: ...2...

Страница 3: ...eling section Updated Commissioning section V4 1 18 08 2021 Updated links Updated Commissioning Document V5 0 23 08 2021 Updated to reflect product changes associated with the removal of 4G dongle and...

Страница 4: ...Installation site selection B Installation III Electrical connection A Input output connections B Running current transformer tails C Labeling IV Commissioning A Preparing the SolShare for commissioni...

Страница 5: ...upport allumeenergy com au with any queries List of supplementary documents available online For most up to date versions of all documents including this Installation Manual scan this QR code or go to...

Страница 6: ...er name Company Electrician license number Allume SIP training certification number SolShare Connection Unit Connected eg Apt 1 Unit B Common light power No connection Single Phase Three Phase R1 W1 B...

Страница 7: ...appears at grounding points within the SolShare equipment This symbol is also used in the manual Handling and Safety Instructions SAFETY SYMBOLS INFORMATION The following safety symbols are used in th...

Страница 8: ...uipment Any violation could result in personal death or injury or damage to the device Installation is only to be conducted by a certified electrician This guide is provided to help the installer unde...

Страница 9: ...itch Inverter Supply is required on each output ideally located within the unit main switchboard between the SolShare and each unit s main switch In series with this additional SolShare Maintenance Is...

Страница 10: ...able commissioning and ongoing monitoring Do not mount the SolShare on flammable wall material 90 Mounted Vertically Do not mount the SolShare near flammable material or gases 90 Mounted Vertically En...

Страница 11: ...ecure the mounting brackets to the chosen wall for installation Allume Energy recommend using the provided fasteners to attach the brackets into a suitable stone or masonry wall If another wall materi...

Страница 12: ...inals Retain screws to replace later Important The cover should lock into place when it s pulled up properly Before beginning wiring ensure cover is locked in place by pulling down firmly To bring cov...

Страница 13: ...ram above Warning The SolShare may divert all solar energy to any one unit in a point in time As a result all input output cables should be sized for maximum solar energy output The AC cables Please c...

Страница 14: ...d have been designed in accordance to the SolShare System and SLD Design Guidelines If no project SLD exists please contact project owner or system design engineer For ease of isolation of the SolShar...

Страница 15: ...output power cables to appropriate length to reach from SolShare Maintenance Isolators Grid Label both ends of these cables with the tenancy number 3 If using SolShare Maintenance Isolators Grid Run c...

Страница 16: ...se 3 Repeat steps 1 2 for white and blue phase connector blocks 4 Plug each CT connector block into the corresponding socket of the SolShare Important Make sure colours and orientation of connectors a...

Страница 17: ...on inverter s before working on meter panel Warning Shared Solar System To isolate a single unit 1 Turn off their MAIN SWITCH INVERTER SUPPLY 2 Turn off their MAIN SWITCH NORMAL SUPPLY X X X X X X M1...

Страница 18: ...nter the SSID and password of the Wifi network that you want the SolShare to connect to 4 Once you see a confirmation page in the browser wait for the SolShare to reboot 5 Disconnect your device from...

Страница 19: ...19...

Страница 20: ...tallations in Australia Specifications are subject to changes without advanced notification For the most up to date documentation vist www allumeenergy com Allume Energy Ltd www allumeenergy com info...

Отзывы: