USER’S MANUAL
V-line 899x.xxx
3
The information included in the present instructions are mandatory and the manufacturer does not
accept any responsibility for any damage due to their non-observance.
The dispenser is complicated equipment providing many important functions.
Prior to putting into operation tanks and the piping system shall be cleaned and fuel purity shall be
checked. Also el. power distribution and correct wiring shall be inspected to prevent injury by el.
current and to provide explosion proofness – fuels are flammable liquids of the 1
st
and 2
nd
danger
class!
The manufacturer tests each dispenser considering the function, safety and metrology. Each delivery
shall include the instructions for attendance, maintenance and installation, EC declaration of conformity
and a service book identifying dispenser components. The dispenser, produced with high precision and
care, secures reliable and safe operation. Principal safety regulations protecting the user against injury
shall be kept during operation and maintenance and the dispenser shall be prevented from damage.
ATTENTION!
No modifications of the dispenser equipment are allowed without producer’s written
approval!
Important instructions for installation and operation:
a)
Study the instructions for attendance, maintenance and installation and other manufacturer’s
documents included within dispenser accessories before you start to handle the equipment.
b)
Check the dispenser delivery completeness and inform the manufacturer immediately in case of any
discrepancies or damage.
c)
The dispenser shall be stored in a dry and protected room before it is installed at the filling station.
d)
Prior to dispenser installation check the completeness of the filling station technology according to
the valid design, check the connecting dimensions of the foundation frame including the piping
system outlet.
e)
Rinse the process equipment (piping) through the filtration equipment until impurities are removed.
f)
The dispenser requires the connection of the vapour return piping of min. DIN 16 – we recommend
DN 25.
g)
Wiring and inspection of the dispenser shall be carried out.
h)
When putting the dispenser into operation, proceed according to the point 7 of the present
instructions.
i)
A metrology authority specialist shall perform function test and metrology checking.
j)
Being these conditions fulfilled, after the approval of a state supervision authority and the
verification of a metrological office representative, usual operation can be started.
k)
Only qualified and trained staff of a service company can perform service and installation. Service
procedures shall be performed in compliance with the operation regulations of the filling station. The
manufacturer is not responsible for damages due to the incompetence of the staff.
l)
The owner can only start dispensing when the filling station inspection is finished and a
metrology authority carries out metrological verification of the dispensers.
m)
When fuels are pumped, basic hygienical precautions shall be adhered. The owner shall enable
the customer to use protective gloves.
SAVE FOR FUTHER USE!
Содержание MINOR V-line 899 Series
Страница 2: ......
Страница 25: ...USER S MANUAL V line 899x xxx 21 Pic 6 Pic 7 ...
Страница 28: ...V line 899x xxx USER S MANUAL 24 Pic 15 Pic 16 ...
Страница 29: ...USER S MANUAL V line 899x xxx 25 Pic 10 Scheme of inputs and outlets of the unit VAPORIX Control ...
Страница 64: ......
Страница 69: ...USER S MANUAL V line 899x xxx Enclosure no 5 View of dispensers V line 899x 4x2 series ...
Страница 80: ...V line 899x xxx USER S MANUAL Enclosure no 16 V line dimensions of V line 899x 6x4 S P dispensers ...