Installation and Commissioning Guide
Variable Capacity Commercial
13
Installation and Commissioning Guide- Package Ducted Variable Capacity Commercial
Doc. Part No. 0525-076 Ver. 3 210414
08. Unit Lifting Procedure
WARNING
WH&S regulations must be observed and will take precedence during lifting process.
Crane Lifting Method
Crane lifting method is recommended for high rise lifting.
Fig. 1
Connect the loop ends
of slings into shackle
Provide rubber pads
to prevent damage
to the unit
RUBBER
PADS
LIFTING POINT
Lifting point is located at each corner of
the unit (4 Total). Size: Ø17.5 mm
EQUIPMENT REQUIRED FOR CRANE LIFTING:
• 1 x Shackle
• 2 x Nylon Slings
• Spreader Bar
NOTE
Refer to Unit Dimensions and Clearances section for unit weight before selecting shackles and slings.
Содержание PKV160T
Страница 57: ...THIS PAGE WAS INTENTIONALLY LEFT BLANK ...
Страница 58: ...THIS PAGE WAS INTENTIONALLY LEFT BLANK ...
Страница 59: ...THIS PAGE WAS INTENTIONALLY LEFT BLANK ...