11. Routine inspections

 

 

•  The routine inspections must be performed by 

our personnel or by the customer's personnel so 
long as they are sufficiently qualified and 
possess detailed knowledge about the apparatus

•  Before proceeding with any operation, always 

make sure that the apparatus is in the open 
position with the springs discharged

•  Before opening the door, always check the 

position of the feeder disconnector and earthing 
switch by means of the mechanical signals

•  The apparatus is guaranteed to be maintenance-

free for the first 36 months from delivery

11.1  General information

During normal service, the switchgear is 
maintenance-free. Any interventions required 
basically depend on the severity of the service 
conditions, i.e. on various different factors such as 
the frequency of the operations, the interrupted 
current values, the relative power factor and the 
installation site.
For precautionary reasons, an inspection schedule 
is given in the table in the following section, along 
with the frequency with which the equipment must 
be checked. It is advisable to comply with the 
indications in the table for the first interventions. 
Optimal time limits for carrying out successive 
operations can be established on the basis of the 
results obtained during the routine inspections.
It is advisable to record all the operations 
performed in detail on a maintenance card and 
service book, along with the date, description of the 
fault and reference data allowing the device to be 
identified (see chap. 2). 
Refer to article 11 of standard IEC 62271-1 if further 
details are required. Do not hestitate to call us if 
problems arise. It is always a good idea to inspect 
the apparatus (screw and bolt tightness - abnormal 
heating, etc.) a few months after it has been put into 
service.
The following table gives the indicative frequencies 
with which inspections should be made.

 

  Do not put the apparatus into service if 

the test result is negative.  
Call us if necessary

11.2  Inspection schedule

Part liable to 
inspection

Inspection 
frequency

Operation required

1 Perform a 

few 
mechanical 
closing and 
opening 
operations

3 years

Make sure that the operating 
and transmission levers 
function correctly.  
The apparatus must operate 
regularly without stopping in 
intermediate positions and 
the applied torque must not 
exceed 200 Nm

2 Visual 

examination 
of the 
insulating 
parts

3 years, or 
depending on 
the degree of 
pollution in 
the 
environment

The insulating parts must be 
free from any built-up dust, 
dirt, cracks, traces of surface 
discharges or damage
Remove the dust and dirt 
with a vacuum cleaner and 
clean, dry cloths

3 Auxiliary 

contacts

5 years

Make sure that operation and 
the signals are correct

4 Auxiliary 

circuit 
conductors

5 years

Check whether any of the 
wiring fasteners is slack or 
broken and make sure that 
the connections are well 
tightened

5 Interlocks

5 years

Make sure that the devices 
function correctly (sect. 5.4 - 
6.0)

6 Measurement 

of the 
insulation 
resistance

5 years

See sect. 10 (table)

7 Operating 

mechanism

3 years

Check that the operating 
mechanism is clean

Содержание UniSec DY800

Страница 1: ...tions for the operating sequence of all UniSec DY800 cubicles 12 7 Voltage and phase correspondence indicator 13 8 Installation 14 9 Cable test 24 10 Putting into service 25 11 Routine inspections 26 12 Quality of the products and environmental protection 27 13 SF6 gas 28 Installation service and maintenance instructions for 24 kV prefabricated assemblies with arc proof metal enclosures and multi ...

Страница 2: ...are carried out by qualified personnel with suitable knowledge of the apparatus To ensure that the installations are built in accordance with the rules of good working practice and safety in the work place make sure that the regulatory and legal requirements are complied with during installation putting into service and maintenance The personnel who access the switchgear must possess PES or PEI qu...

Страница 3: ...he ground so that the overall height is 4 m maximum The surface of the loading platform must be non slip with a high coefficient of friction The assemblies must be arranged cross wise and back to back on the platform with suitable material in between so as to prevent them from touching and pressing against each other Frame members must be arranged on the platform so as to space out the units and p...

Страница 4: ... goods fail to correspond immediately inform ABB either directly or through your representative or supplier and the haulage contractor that made the delivery The cubicles are supplied solely with the accessories specified at the time of order and validated in the order confirmation The following items are to be found inside the cubicles instruction manual a packet containing screws nuts washers bu...

Страница 5: ...on when using a lift truck for handling purposes UniSec switchgear is normally placed on a wooden pallet and fastened with four bolts one per corner For handling purposes the switchgear can be lifted by crane using ropes with snap hooks conforming to the safety standards inserted through the eyebolts on the top of the units or by fork lift truck In this case the forks must be inserted at the sides...

Страница 6: ...30 A Admissible rated short time withstand current 16 kA Electrical life class ref IEC 62271 100 E2 Admissible short time peak current value 40 kA Rated short circuit duration 1 s Rated short circuit breaking capacity 16 kA Rated operating sequence O 0 3 sec CO 30 sec CO Mechanical life 10000 operations Class M2 Rated breaking current values circuit mainly active 630 A vacuum transformer 6 3 A no ...

Страница 7: ...C A C B A C B 7 DISTRIBUTION SOLUTIONS 5 2 Overall dimensions DY800 116 DY800 216 DY800 316 Dimensions mm Weight kg A B C DY800 116 500 1850 1050 275 DY800 216 500 2250 1050 302 DY800 316 700 1950 1150 305 ...

Страница 8: ...aratus with 3 positions and circuit breaker small size low amount of SF6 used for insulation ease of use All the cubicles are internal arc proof in accordance with the provisions established by standard IEC 62271 200 The IAC classification of the various types restricted to authorized persons alone class A complies with the 5 criteria established by the standard The 3 types of UniSec DY800 cubicle...

Страница 9: ...5 3 5 Characteristics of the circuit breaker operating mechanism The circuit breaker is equipped with a three pole operating mechanism with the following circuits and devices a three pole voltage start up closing circuit a three pole voltage start up opening circuit an anti pumping device to prevent further closings other than the first when opening occurs during the initial closing request This d...

Страница 10: ...ector SL in the open position and earthing switch ST in the closed position both with moving contacts locked at end stop This interlock is created electrically by cutting off the electrical controls of circuit breaker I 4 It must only be possible to open the cubicle door in conditions of safety i e with feeder disconnector SL open and earthing switch ST closed This condition is obtained with a pad...

Страница 11: ... lever is in the lever seat of earthing switch ST Insertion of the operating lever acts on a micro switch which cuts off the power supplied to the control circuits of circuit breaker I 5 5 5 Interlock between feeder disconnector SL and circuit breaker I This is a mechanical lock of the inhibiting type that prevents the operating lever of feeder disconnector SL from being inserted into its seat if ...

Страница 12: ...between the disconnector and circuit breaker in the upward direction Fully insert the operating lever into its seat 10 in earthing switch ST Turn the operating lever clockwise until the operation has been completed Remove the operating lever Check that the indicator 9 confirms that closing has occurred by displaying letter I in black on a yellow background 4 Open the door by pulling the handle up ...

Страница 13: ... earthing switch is closed before accessing the base of the detector 1 where the shielded cables are connected The signaling devices 2 can be connected and disconnected in the base 1 when the cubicle is live Make sure that the enclosure of the signaling device is earthed while the signaling devices are being connected and for as long as they remain in that position When the signaling device is dis...

Страница 14: ...away from the area overlooking the fumes exhaust stacks and do not install apparatus in that area Maximum ambient air temperature 40 C Minimum ambient air temperature 15 C Relative humidity 95 without condensation Altitude 1000 m Comply with the indications in the product standards if other installation conditions are involved Please consult us for special installation requirements The areas throu...

Страница 15: ...TION SOLUTIONS DY800 216 A mm 450 B mm 100 C mm 1200 D mm 100 Dimension C represents the space required to withdraw the cubicle A mm B mm C mm 1200 D mm 100 Dimension C represents the space required to withdraw the cubicle DY800 116 ...

Страница 16: ...n electric arc occurring inside the cubicle is very remote If it should occur proceed as described below to eliminate the fumes UniSec DY800 116 and 216 Internal arc in the busbar duct open the flap 1 to allow the fumes to flow into the stack 2 the cable compartment flap 3 remains closed fumes escape from the exhaust vent of the stack 4 Internal arc in the cable compartment open the flap 3 to allo...

Страница 17: ...for connection of the medium voltage circuit from the bottom The front part of the roof of UniSec cubicles has a duct for routing the auxiliary circuit cables Make the relative routing holes under each cubicle before it is installed The foundation layout is shown in the figure The switchgear can be fastened straight to the floor by inserting expansion plugs into the fixing holes The fixing surface...

Страница 18: ...ghtening them move the second cubicle close to the first so that their sides touch each other fit the M4 screws into the holes marked X and fully tighten the bolts into the adjacent cubicle fit the M10 screws into the holes marked Y and fully tighten the bolts into the adjacent cubicle Repeat these operations for the successive cubicles and after they have been joined together fix the cubicles to ...

Страница 19: ...tion is horizontal and well leveled with 2 1000 maximum flatness 2 mm with respect to a square meter place the base in the substation 20 mm from the right hand wall and 190 mm from the rear wall and mark the positions of the holes drill the floor insert 4 expansion plugs and fix the base in place Make sure that the cable outlet 2 in the base is on the left It the unit must be positioned in the lef...

Страница 20: ...20 UNISEC DY800 ED 4 ACCORDING TO E DISTRIBUZIONE SPECIFICATIONS INSTALL ATION MANUAL End panel Panel assembly sequence Comply with the numbered sequence in the figures below to assemble the panels DY800 116 panel Detail A Detail B View from above Clamps 8 Installation Slot in joint ...

Страница 21: ...ON SOLUTIONS tighten all the screws Fit the roof in place Upper cover panel DY800 316 panel End panel fixing points Front panel Upper cover panel Tighten all the screws Tighten the end plate screws Tighten all the screws Position the roof Slot in joint ...

Страница 22: ...g insulators is perfectly clean and degreased Repeat the operations described in the previous paragraph for the central phase detail D Make sure that the strip A is also connected Only couple the busbars for the remaining phases since the strips are already connected comply with the previously described procedure Tightening torque 60 Nm max 8 7 2 Earthing busbars The earthing busbar is routed long...

Страница 23: ...ternal connection between the motor operated control and telecontrol extension unit is made with multicore cable equipped with flying connectors The figure below illustrates the route inside the cubicle of the cables that connect the current transformers the toroidal transformer for homopolar protection and the RG apparatus Cable route inside the cubicle Flexible metal tubes inside the cubicles al...

Страница 24: ...g ensure that the part of the installation in which the work must be performed is in a safe condition Connection of cables for test purposes applied voltage and troubleshooting alters the characteristics of the switchgear Those who do this must ensure compliance with the correct procedures in order to guarantee safe conditions for the workers Obligatory conditions when performing voltage tests on ...

Страница 25: ... and those included in the configuration have been installed correctly Make sure that all panels for protection against accidental contact have been installed correctly Check that the interlocks function correctly and that the keys if any are correctly joined with a welded ring if they are required for the interlocks Check that the mechanical operating mechanisms can be operated by applying 200 Nm...

Страница 26: ...k along with the date description of the fault and reference data allowing the device to be identified see chap 2 Refer to article 11 of standard IEC 62271 1 if further details are required Do not hestitate to call us if problems arise It is always a good idea to inspect the apparatus screw and bolt tightness abnormal heating etc a few months after it has been put into service The following table ...

Страница 27: ...own by Standard ISO 14001 ABB offers its skills and assistance to facilitate product recycling and disposal at the end of life stage Compliance with the local regulations when disposing of products is always mandatory 12 2 Disposal methods The products can be disposed of by means of heat treatments in incineration systems or by storage in dedicated areas Material Recommended disposal method Metals...

Страница 28: ...ic If the overpressure valve fails due to events involving high arc energy levels persons must not enter the area before it has been subjected to intensive ventilation A suitable filter class FFP3 is required for filtering the nanoparticles during the cleaning and disassembly operations following failure of the overpressure valve due to high arc energy levels ...

Страница 29: ...29 DISTRIBUTION SOLUTIONS Notes ...

Страница 30: ...contactcenters More service information abb com service Copyright 2018 ABB All rights reserved The data and illustrations are not binding We reserve the right to make changes in the course of technical development of the product 1VCD601365 Rev A en Unisec DY800 Installation manual Ed 4 e Distribuzione 2018 09 mt ...

Отзывы: