Procedure
1. Make the custom foundation.
Caution: Make sure that
the top surface of the
foundation is above the
ground level, to prevent
intrusion of water.
2. Guide the cables into the holes (C1)
to (C4) of the foundations. For the
relation between the cables and the
.
3. Install the foundation in the hole.
4. Put the cables through the openings
in the foundation. Apply the full cable
slack.
For the cable slack, refer to section
5. Fill the foundation with gravel or another substance to prevent rodents to enter
the cabinet.
C1
C3
C4
C2
Pre-installation
9AKK107992A2254-EN | 005
31