6
Installation
6.1
General installation procedure
Preliminary requirements
•
The AC input cable is
available.
•
The foundations for the
cabinet is prepared.
•
All cables are in the cable
conduits and the full cable
slack is applied.
•
The substation is
prepared.
•
The site is prepared.
•
There is no voltage on
the AC input cable during
the complete installation
procedure.
•
Tools for installation. Refer
to section
Procedure
1. Do the mechanical installation of the power cabinet. Refer to section
.
2. Do the mechanical installation of the charge post. Refer to section
.
3. Do the electrical installation of the power cabinet. Refer to section
.
4. Do the electrical installation of the charge post. Refer to section .
5. Prepare for commissioning. Refer to section
6.2
Mechanical installation of the power cabinet
6.2.1
Install the power cabinet - general procedure
Preliminary requirements
•
The cabinet is above the foundation.
Procedure
1. Remove the plinth covers of the power cabinet. Refer to section
2. Install the cabinet on the foundation. Refer to section
.
3. Open the cable inlets. Refer to section
.
4. Guide the cables to the power cabinet. Refer to section
5. Close the cable inlets. Refer to section
6. Install these parts:
a. Cover plate of the foundation. Refer to section
b. Plinth covers of the power cabinet.
7. Replace the eye bolts on the power cabinet with the caps. Refer to section
.
Installation
9AKK107992A2254-EN | 005
37