![ABB RED670 Relion 670 series Скачать руководство пользователя страница 276](http://html.mh-extra.com/html/abb/red670-relion-670-series/red670-relion-670-series_commissioning-manual_3169276.webp)
Test the correct functionality by simulating different kind of faults. Also check that
sent and received data is correctly transmitted and read.
A test connection is shown in figure
. A binary input signal (BI) at End1 is
configured to be transferred through the communication link to End2. At End2 the
received signal is configured to control a binary output (BO). Check at End2 that
the BI signal is received and the BO operates.
Repeat the test for all the signals configured to be transmitted over the
communication link.
IEC07000188 V1 EN-US
Figure 56:
Test of RTC with I/O
11.17
Basic IED functions
SEMOD52026-1 v1
11.17.1
Parameter setting group handling SETGRPS
M11369-2 v4
Prepare the IED for verification of settings as outlined in section
11.17.1.1
Verifying the settings
M11369-4 v4
1.
Check the configuration of binary inputs that control the selection of the
active setting group.
2.
Browse to the
ActiveGroup
menu to achieve information about the active
setting group.
Section 11
1MRK 505 378-UEN A
Testing functionality by secondary injection
270
Line differential protection RED670 2.2 IEC
Commissioning manual
Содержание RED670 Relion 670 series
Страница 1: ...RELION 670 SERIES Line differential protection RED670 Version 2 2 IEC Commissioning manual ...
Страница 2: ......
Страница 18: ...12 ...
Страница 36: ...30 ...
Страница 68: ...62 ...
Страница 72: ...66 ...
Страница 108: ...102 ...
Страница 278: ...272 ...
Страница 282: ...276 ...
Страница 288: ...282 ...
Страница 306: ...300 ...
Страница 307: ...301 ...