![ABB RED670 Relion 670 series Скачать руководство пользователя страница 245](http://html.mh-extra.com/html/abb/red670-relion-670-series/red670-relion-670-series_commissioning-manual_3169245.webp)
Command function with continuous unblocking (
Unblock = 1)
M13868-76 v6
Procedure
1.
Activate the guard input signal (CRG) of the IED.
2.
Using the scheme selected, check that a signal accelerated trip (TRIP) is
obtained when the guard signal is deactivated.
11.11.1.6
Completing the test
M13868-84 v6
Continue to test another function or end the test by changing the
TESTMODE
setting to
Off
. Restore connections and settings to their original values, if they were
changed for testing purposes.
11.11.2
Phase segregated scheme communication logic for
distance or overcurrent protection ZC1PPSCH
GUID-33B76F26-DEEF-46C3-A66F-A8713B50E413 v1
Prepare the IED for verification of settings outlined in Section
.
Check the scheme logic during the secondary injection test of the impedance
protection functions.
Activating of the different zones and phases verifies that the CSLx signal are issued
from the intended zones. The CSLx signal from the independent tripping zone must
have a
tSendMin
minimum time.
Check the tripping function by activating the CRLx inputs with the overreaching
zone used to achieve the CACCLx signals.
It is sufficient to activate the zones with all types of fault with the secondary
injection.
11.11.2.1
Testing permissive underreaching
GUID-F8C6F099-5C88-466A-8C00-7211981B03B9 v1
1.
Activate the receive (CRLx) signal in the IED.
2.
Apply healthy normal load conditions to the IED for at least two seconds.
3.
Apply a fault condition within the permissive zone.
4.
Check that correct trip outputs, external signals, and indications are obtained
for all the actual types of fault generated.
5.
Check that other zones operate according to their zone timers and that the
send (CSLx) signal is obtained only for the zone and phase configured to
generate the actual signal.
6.
Deactivate the receive (CRLx) signal in the IED.
7.
Check that the trip time complies with the zone timers and that correct trip
outputs, external signals, and indications are obtained for the actual type of
fault generated.
1MRK 505 378-UEN A
Section 11
Testing functionality by secondary injection
Line differential protection RED670 2.2 IEC
239
Commissioning manual
Содержание RED670 Relion 670 series
Страница 1: ...RELION 670 SERIES Line differential protection RED670 Version 2 2 IEC Commissioning manual ...
Страница 2: ......
Страница 18: ...12 ...
Страница 36: ...30 ...
Страница 68: ...62 ...
Страница 72: ...66 ...
Страница 108: ...102 ...
Страница 278: ...272 ...
Страница 282: ...276 ...
Страница 288: ...282 ...
Страница 306: ...300 ...
Страница 307: ...301 ...