Electrical installation of the control box
L
M
15.10 Connect the cable reel interlock cable CR
Preliminary requirements
Procedure
1. Strip the insulation from the
cable. For the specification,
refer to section
20.12.11
2. Prepare the wires:
a. Twist the shield mesh.
b. Strip the wires.
For the specification, refer
to section
20.12.11
3. Make sure that any unused wires
are insulated and cannot touch
metal parts.
4. Loosen the screws on the terminals (L), (M).
5. Connect these wires:
a. X1-41 (L) DC+24V to cable reel interlock
b. X1-42 (M) NC to cable reel interlock
6. Tighten the screws to the correct torque. For the specification, refer to section
2
0.5
.
6AGA000007-0611-EN | 001
75
Содержание HVC-C 100-150 kW
Страница 1: ...Installation manual HVC C 100 150 kW Overnight Copyright ABB All rights reserved CCS and CR variant ...
Страница 42: ...P a g e l e f t i n t e n t i o n a l l y b l a n k 42 6AGA000007 0611 EN 001 ...
Страница 79: ...P a g e l e f t i n t e n t i o n a l l y b l a n k 6AGA000007 0611 EN 001 79 ...
Страница 106: ......