Procedure
1. Remove the nuts (A), washers (B)
and wire end rings (C) from the
bolts on the busbars (D) and (E).
2. Prepare the DC cables:
a. Cut the cables (F) and (G) to the
correct length to reach the
bolts on the busbars.
b. Strip the cables from
inslulation. Make sure that the
strip length agrees with the
wire end rings (C).
c. Attach wire end rings (C) to the
end of the wires.
3. Connect these cables:
a. DC- cable (G) on the bolt on the
negative busbar (E)
b. DC+ cable (F) on the bolt on the positive busbar (D)
4. Install washers (B) and nuts (A) on the bolts.
5. Tighten the nuts to the correct torque. For the specification, refer to section
C
D
E
F
G
B
A B
Electrical installation of the control box
74
6AGA000007-0611-EN | 001
Содержание HVC-C 100-150 kW
Страница 1: ...Installation manual HVC C 100 150 kW Overnight Copyright ABB All rights reserved CCS and CR variant ...
Страница 42: ...P a g e l e f t i n t e n t i o n a l l y b l a n k 42 6AGA000007 0611 EN 001 ...
Страница 79: ...P a g e l e f t i n t e n t i o n a l l y b l a n k 6AGA000007 0611 EN 001 79 ...
Страница 106: ......