Installation and commissioning guide
1ZSC000563-ACF EN, REV. A, 2020-06-25
6.
Apply Molykote Multilub to the M10 bolts (6).
G001875
7.
Install the M10 bolts (6) and plain washers (7).
8.
Tighten the M10 bolts (6) in a crosswise
sequence.
CAUTION!
Make sure that the outer terminal
moves straight down. Turn each bolt a
little, and then the next bolt, until all
bolts can be tightened to the correct
torque.
G006898
Torque
40 ±4 Nm
9.
Tighten the M8 bolts (24).
Tighten the bolts in a crosswise sequence.
G006900
Torque
20 ±2 Nm
10.
Install the external connections. Refer to the documentation from the supplier of the external
connection.
End of instruction