Installation and commissioning guide
1ZSC000563-ACF EN, REV. A, 2020-06-25
5.
Install the washers and nuts. Tighten the nuts in a
crosswise sequence.
G000719
Torque
Please refer to the transformer
documentation.
6.
Install the draw-rod nut (10):
1.
Apply a generous quantity of Molykote
Multilub to the nut (10), and the threads of
the draw rod.
2.
Install the washer (11) and nut (10) on the
draw rod, tighten with your fingers.
3.
Remove excess Molykote Multilub with a rag.
CAUTION!
If the nut (10) is not lubricated correctly,
it will not be tighten to the correct
torque. This can cause the bushing to
fail.
G005063
7.
Tighten the draw-rod nut (10).
NOTE!
Make sure that more than 10 mm of
the threads on the upper draw rod (35)
is remaining.
G005062
Torque
10 Nm
8.
Remove the pull-through cord (12).