INSTALLATION
Assembly (Continued)
Prior to commencing the next stages it is important that the
utmost care is taken with operating the hoist until all posts are
safely secured to the concrete.
21. With the power connected to the hoist, press the up button to raise the
hoist approximately 300mm. At this point, remove the blocks of timber
from under the transverse beams. Now check that all hydraulic lines &
wire cables are in their correct position and have not caught on each
other or the hoist.
22. Raise the hoist to full height taking care not to over stroke the hydraulic
cylinder under the left platform. Adjust the limit switch on the safety
ladder inside the control post. It must make contact with the safety
striker on the front transverse beam. (See Picture 7)
23. With the hoist at full height remove the D shackles on the cables at the
end of the hydraulic cylinder under the left platform. Run the hoist up
and down several times. By doing this it will allow the hoist to self level.
24. Once the hoist has self levelled, re-fit the D shackles on the cables and
lock into place
.
At the same time ensure the twin lock
nuts on the head
of the hydraulic cylinder are locked into position.
25. Now lower the hoist so that it is only 100mm from the ground.
26. Check that all posts are in the correct position, ensuring that they are
square to each other as well as horizontally level. Depending on the
install situation, the posts may need to be shimmed. Before bolting it is
also important to ensure that the posts are vertically level in both
planes.
27. Once all posts are correctly positioned and level, they are ready to be
bolted.
28. Drill the 4 x 16mm holes of the posts into the concrete and fix the
column with 4 x 16mm x 140mm Tru-Bolts. Ensure the bolts are now
tightened.
29. Once bolted down & tightened, check all levels.
30. Install the Wheel Stops at the front of each platform.
31. Install the Run-Up Ramps at the rear of each platform.
32. With the hoist on its locks and with no load on the wire cables, grease
the 4 Transverse Beam Pulley Pins & the 4 Platform Pulley Pins. While
pumping the grease into the pins, ensure you rotate the pullies by
hand. This ensures even distribution of grease.
33. The final step in the installation process is to adjust the wire cables. As
the levels have already been checked, ideally all four locks should click
simultaneously when the hoist is raised. To test, raise the hoist to full
height, and then lower half way down, taking note of the clicks from the
safety locks. If the clicks are out of sync adjust the relevant cables to
overcome. Once the cables have been adjusted and the clicks are
synchronised, lock both of the nuts on each of the cable ends.
14
Содержание AutoLift AL-6000A
Страница 10: ...Dimensions AL 6000S2 9 ...
Страница 18: ...Parts List 17 ...
Страница 19: ...18 ...
Страница 25: ...Air Line Diagram 24 ...
Страница 26: ...Electric motor jumper pins 25 ...
Страница 27: ...26 ...
Страница 28: ...How to operate Jack 27 ...